Shaoxing Zhenya Steam Supply& Power Generating Plant was founded in March 1995. Now it has 150 employees and 90 mu of land. We have 2 steam generating sets with 3000 kw/h and 1 with 6000 kw/h, totaling 51000 kw/h with 5 generating sets, 2 sets of boilers with 20 tons, 1 with 25 tons, 2 with 75 tons, 2 with 150 tons, totaling 525 tons witih 7 boilers. Annual heat is 1.94 million tons, and electricity 257.64 million electric degrees. Production of heat and electricity saves energy, raise the efficiency of heat-providing and reduce air pollution.
|